Zoning, Property Information, and Building Permit Records
Get zoning and property information that is specific to the site. Zoning information can be obtained through ZIMAS (Zone Information and Map Access System).
Obtain site specific building permit records. Permit records may be obtained online, in-person, or by mail. More information on obtaining building permit records may be found here.
Design and Draw Plans
Create a submittal package, including the existing building permit records, with the following minimum plan requirements, drawn to scale:
- Plot plan – Show location of the street, street name, lot dimensions, existing buildings, area(s) of work, parking layout, driveway location, yard setbacks from property lines and between buildings.
- Floor plan – Show proposed work and adjacent room(s), (if applicable), door and window sizes and location.
- Building Elevations/Cross Sections – Exterior elevations for new construction, detailing all exterior walls, projections and cross sections in each direction.
- Foundation Plan – Show foundation size (width and depth), along with slab on grade thickness. For raised floor construction, show size and direction of floor joists.
- Roof Framing – Show roof rafters and ceiling joists’ size and direction.
- Energy Conservation – Energy calculations and Certificate of Compliance (CF1R). See energy.ca.gov/title24 for
more information.
- Green Code – (if applicable), material specifications, notes and details.
More detailed document submittal requirements can be found from the Department’s Information Bulletins.
Plan Submittal and Plan Check Process
Submit the package to the Department of Building and Safety. Plans will accepted through ePlanLA and at any of our Development Service Center locations. Plans will be reviewed for compliance with
the Zoning and Building Codes. Instructions on how to obtain compliance will be provided on a correction list. Clearances from other City Departments may be required. They include, but are not limited to:
Department of Water and Power (DWP): Work adjacent to or within ten feet of DWP easements
- Fire Department: Hydrants and Access
- Department of City Planning: Historical Preservation Overlay Zone (HPOZ), Specific Plan, and/or front yard landscape
- Department of Public Works:
- Bureau of Engineering (BOE) – Curb cuts, sewer connection, address approval, and/or site drainage
- Bureau of Street Services (BSS) – Urban Forestry Division (UFD) – Removal of trees in parkway and/or onsite trees
- Bureau of Sanitation (SAN) – Low Impact Development and Storm Water Pollution Mitigation
Once all corrections have been made and all clearances have been obtained, the permit will be issued, plans will be stamped approved, and construction can commence.
Construction and Inspection
Begin construction. Should the construction vary from the approved plans, please return to plan check for approval.
To schedule an inspection:
- Call 311, (866) 4LACITY, or (213) 473-3231
- Go to the mobile app, LADBS Go
- Go online, ladbs.org
Groundwork: Schedule inspection for footing excavation when all reinforcing steel, forms, and groundwork plumbing and electrical have been installed but before concrete is poured.
Rough: Schedule inspection when all framing work as been completed and plumbing, electrical, wiring, and heating ducts have been installed but before any of the work is covered.
Final: Schedule inspection when construction has been completed.
Certificate of Occupancy
Once the final inspection has been approved, a certificate of occupancy will be issued for additions, new buildings, and conversions. Remodels/repair of existing building do not require a new certificate of occupancy.